The route to environmental clearances
Under the Environmental Impact Assessment Notification, 1994, amended in 1997, the company seeking environmental clearance submits to the concerned state pollution control board (SPCB) an executive summary (ES) of the project
The SPCB gives a 30-day notice for environmental public hearing with details of the time, date and venue. The notice is published in two widely-circulated newspapers, one in the local language. During this time, the public is provided access to the ES.
On the notified day, a public hearing is held, on the basis of which SPCB gives a No Objection Certificate.
The company concerned applies to the Union ministry of environment and forests for clearance; provides EIA or environmental management plan, details of the public hearing and NOC.
Reports submitted is evaluated and assessed by MEF; prepares recommendations also based on details of public hearing.
Assessment is completed within 90 days of receipt of application and completion of the public hearing. The decision is conveyed within 30 days thereafter. If no comments are received within the time limit, the project is given "deemed' consent.
Related Content
- Order of the National Green Tribunal regarding construction of road affecting a water system, village Malla Dhadhariya, Almora district, Uttarakhand, 19/10/2022
- Order of the National Green Tribunal regarding illegal operation of Gandanali Black stone quarries, Dhenkanal district, Odisha, 12/09/2022
- Joint Committee report on sand mining in the districts of Gadag, Raichur and Kalburgi, Karnataka, 10/06/2021
- Order of the National Green Tribunal regarding protection of environment along the highways, 03/12/2020
- Report on EC violations by CCL in Piparwar open cast project, Jharkhand, 14/09/2020
- Green Highways (Plantation & Maintenance) Policy-2015