Judgement of the Supreme Court of India on environmental clearance for hydroelectric projects in the state of Uttarakhand dated 13/08/2013
Expressing concern over the proliferation of hydrolectric projects and their impact on the Bhagirathi and Alaknanda rivers, the SC has directed the environment ministry to not grant any environmental clearances to the hydro-electric projects in Uttarakhand.
Judgement of the Supreme Court of India in the matter of Alaknanda Hydro Power Co. Ltd. Vs Anuj Joshi & Others dated 13/08/2013 directing the MoEF as well as state of Uttarakhand not to grant any further environmental clearance or forest clearance for any hydroelectric power project in the state of Uttarakhand until further orders.
See Also
Report: Green norms for green energy
Notification: River Bhagirathi from Gaumukh to Uttarkashi as Eco-sensitiv
Report: Assessment of cumulative impacts of hydroelectric projects
Document: Environmental Clearance to M/s Alaknanda Hydro Power Company
Order: MoEF order to Alaknanda Hydro Power Company.
Report: Srinagar hydroelectric power project.
Notification: Draft Notification on river Bhagirathi.