Question raised in Lok Sabha on Hydro Power Projects in Backward Areas, 16/03/2017. Presently, 44 Hydro-Electric Projects (HEPs) (above 25 MW) with total installed capacity of 11,993.5 MW are under construction in the country. Out of these 44 HEPs, 21 HEPs aggregating to 6429 MW are stalled / stressed due to various reasons. The state-wise details of such HEPs vis-à-vis the reasons for delay in commissioning are given at Annex.