Green light for Mundra UMPP, Sasan awaits clearance
With the ministry of forests and environment (MoEF) giving the crucial environment clearance, implementation of Tata Power's 4,000-mw Mundra ultra mega power project (UMPP) has gathered momentum. However, Reliance Power's 4,000-mw Sasan UMPP is yet to receive the MoEF clearance. The ministry has emphasised the need for an integrated proposal for forest clearance, covering forest area involved in the project limits, and the mining area. While the implementation schedule of the main plant of Sasan project is spread over five years, the development of mines takes about two years. Thus, with the main plant in the process of being implemented, the forest clearance proposal for the mining area can be submitted separately after obtaining an approval for the mining plan. According to power ministry sources, "Power secretary Anil Razdan has recently reviewed the implementation progress of Mundra and Sasan UMPPs. The Coastal Gujarat Power Limited (CGPL)