Response of the NTPC Vindhyachal to the quarterly report of OSC in OA No. 164 of 2018 (Ashwani Kumar Dubey Vs Union of India & Others). Vindhyachal Super Thermal Power Station Ltd. has informed that 100 per cent ash utilization has been achieved.
FGD installation work is in progress for all the units. NOx limit has been achieved in unit 10 with combustion chamber modification. Action plan is in place to achieve the limit in all other units as per the CPCB time line of December 2022.