Rajasthan aims 3,780 MW solar capacity by April next
-
18/04/2018
-
Economic Times (New Delhi)
JAIPUR: With 20 projects of 1,500 MW capacity in pipeline, Rajasthan is targeting to increase its solar power generation to 3,780 MW by April next year in order to achieve the goal of 7,000 MW clean energy capacity in the next four years.
"The current solar power generation is contributing 10 per cent to the total power consumption in the state and we are targeting to increase it to 17 per cent by 2021," Rajasthan Renewable Energy Corporation Managing Director B K Doshi told .
He said that solar power installation capacity in the state has reached to 2,280 MW by March this year and 20 projects of total 1500 MW are under pipeline and will be commissioned and start generating power by April next year.
"Work on various projects is in full swing. The second phase of Bhadla solar park near Jodhpur has been commissioned (680 MW) and its third phase (1000 MW) is under progress. Of the 1000 MW capacity under the third phase of Bhadla park, 500 MW will be commissioned in September this year and 500 MW by April next year. Fourth phase of 500 MW will also be commissioned by April," he said.
Of the total 1,500 MW projects, which are scheduled to be commissioned by April next year, 10 are of the capacity of 100 Mw each and 10 of 50 MW each, he said.
Other projects which are under the pipeline are Pokran-Phalodi solar park (750 MW), Fatehgarh phase 1B (1500 MW) and Nokh - Jaisalmer (1000 MW).