Nuclear Power Corp of India Ltd (NPCIL) has denied allegation by a Sri Lankan interest group that the Kudankulam plant in Tamil Nadu was leaking radiation, and said the phase 1 of the project would be ready soon and power production would start by April-end. The Sri Lankan group, the …
Large number of farmers and environmentalists will gather at a mega congregation in Mithi Virdi village of Bhavnagar district on Monday to oppose tooth and nail the 6,000 MW nuclear power plant proposed at this coastal site. The congregation comes just a day before the crucial public hearing to be …
The Union budget presented in Parliament on Thursday has provided an allocation of Rs. 150 crore for a neighbourhood development project at Kudankulam in Tamil Nadu, where a 2000 MW nuclear power plant is coming up. The provision follows the Tamil Nadu government’s announcement of a Rs. 500 crore development …
The report is an Environmental impact assessment report for the proposed 2x700 MWe PHWR Chutka Madhya Pradesh Atomic Power Project (CMPAPP) of Nuclear Power Corporation of India Limited (NPCIL). The objective of the EIA study report is to take stock of the prevailing quality of environment, to assess the impacts …
Nuclear Power Corporation of India Ltd ( NPCIL) and French conglomerate Areva won’t be able to exchange documents for the final works contract on the supply of two evolutionary pressurised reactors (EPRs) for the Jaitapur nuclear project in the presence of visiting French President François Hollande on Friday. Negotiations between …
The Maharashtra government’s decision to give increased compensation to the Project-Affected People (PAP) of the proposed 9900-MW Jaitapur Nuclear Power Plant (JNPP), in the backdrop of French President Francois Hollande’s visit to India, has met with serious opposition. The farmers and fishermen fighting against the JNPP on Thursday rejected the …
MUMBAI: The state government has approved a hefty compensation package for farmers opposing the Jaitapur nuclear power plant. The revised package offers affected farmers Rs 22.5 lakh per hectare instead of Rs 1.5 lakh to Rs 4 lakh announced earlier. The Nuclear Power Corporation of India Limited (NPCIL) plans to …
To benefit about 2,300 affected people Nuclear Power Corporation reiterates readiness to spend more on relief, rehabilitation People who stand to lose their land to the Jaitapur nuclear power project in Maharashtra’s Ratnagiri district are to get compensation of Rs 22.5 lakh a hectare, instead of the earlier Rs 50,000 …
Engineers India Ltd has completed a preliminary report for the environmental impact assessment for Nuclear Power Corp of India Ltd’s (NPCIL) proposed 6x1,000-megawatt (Mw) project at Mithivirdi, Gujarat. US nuclear reactor supplier Westinghouse Electric Co has signed a memorandum of understanding with NPCIL, agreeing to negotiate an early works agreement …
Authorities want systems to work “exactly textbook like” before plant is commissioned There was no major issue behind the delay in the commissioning of the 2000 MW nuclear power plant at Kudankulam, Chairman of the Atomic Energy Commission R.K. Sinha told a group of reporters here. Dr. Sinha said that …
To decide on ‘pinnacle protest’ against project commissioning The latest announcement from Minister of State in Prime Minister’s Office V. Narayanasamy on the possible commissioning of Kudankulam Nuclear Power Project in mid-January has compelled the protesters to convene a meeting of community leaders on January 13 at Idinthakarai to decide …
The much-delayed Kudankulam nuclear power project (KNPP) in Tamil Nadu’s Tinulveli district is finally set set to be commissioned within the next two weeks as nuclear scientists have entered the final lap of a series of tests on its safety and efficacy. "Within this month 100%. It will take about …
The much-delayed Kudankulam project is set to be commissioned within the next two weeks as nuclear scientists have entered the final lap of a series of tests on its safety and efficacy. “Within this month 100 per cent. It will take about two weeks,” Ratan Kumar Sinha, Chairman of the …
The joint venture companies are yet to decide on the quantum of the bond or external commercial borrowings NPCIL-Nalco Power Company Limited — a joint venture between Nalco and NPCIL (Nuclear Power Corporation of India Ltd) to set up nuclear plants —will raise a term loan of up to Rs …
Paryavaran Suraksha Samiti demanded that the March 5 environmental public hearing for Mithi Virdi nuclear power plant in Saurashtra's Bhavnagar district be stopped and this EIA report submitted by Engineers India Limited be scrapped as it did not have the necessary accreditation. In October 2009, Government of India has accorded …
Russia has told India that Kudankulam nuclear power plants 3 and 4 would cost “double”, after New Delhi decided that the next two reactors would come under the new civil nuclear liability law, and not be covered by the agreement on Kudankulam 1 and 2, top government sources have told …
Unperturbed by protests against its proposed nuclear power plant in Jaitapur, Maharashtra, the French civil nuclear energy major Areva is now in the closing stages of striking an “early works agreement” with Nuclear Power Corporation of India Limited. This agreement, which is actually a series of studies to ensure that …
In the last lap of its first approach to criticality, the first unit (1000 MWe) of the Kudankulam Nuclear Power Project (KKNPP) in Tamil Nadu is undergoing a battery of tests by engineers of the Nuclear Power Corporation of India Limited (NPCIL). R.K. Sinha, Chairman, Atomic Energy Commission, told The …
Visakhapatnam: The department of atomic energy, under the aegis of the Prime Minister, has accepted the proposal of the Nuclear Power Corpo-ration of India Limited to increase capacity of the Kovvada Nuclear Park from 6,000 MW to 9,500 MW. According to DAE’s earlier clearances, the nuclear park’s capacity was barely …
After taking away cheques for the compensation of their lands acquired for the proposed Gorakhpur Atomic Power Project (GAPP), farmers are now up in arms against the authorities for hike in the payment to almost double the amount they have already received. The authorities, too, have taken a tough stand …