Order of the Supreme Court in the matter of State of Rajasthan & Others Vs Ashok Malik & Others dated 17/03/2025. The SC accepted the statement made in the affidavit by the Chief Secretary, state of Rajasthan to relocate the structures inside the Seven Wonders Park along the Ana Sagar …
Rajahmundry, April 11: The Chief Minister, Dr K. Rosaiah, vowed to make efforts with the Centre to get national project status for the Indira Sagar (Pola-varam), Devadula and Pranahita-Chevella projects. Addressing a public meeting held under the aegis of the district Congress committee at the Government Arts College grounds here …
The three major projects contributing major share to the State Power Scenario are Indira Sagar, Omkareshwar and Interstate Sardar Sarovar Project. Since commissioning, these three hydro power projects in Narmada Valley have yielded 23561.5 mu of power till February, 2010 resulted amounts Rs 4855 cr. The Indira Sagar project over …
THE Supreme Court has allowed the Madhya Pradesh government to resume construction of canal networks of Indira Sagar and Omkareshwar dam projects on the Narmada. On February 25, the court overturned the state high court order that halted the work following a petition by activist Medha Patkar. She had demanded …
RASHME SEHGAL NEW DELHI Non-compliance with environmental norms has led the environment ministry-appointed Expert Apparisal Committee of River Valley Projects (EACRVP) to call for a halt to all work on the Sardar Sarovar Project (SSP) and its feeder Indira Sagar Project (ISP). The two projects are being implemented by the …
NEW DELHI: The Supreme Court on Thursday permitted the Madhya Pradesh Government to go ahead with acquisition of land, excavation and canal network construction work for implementation of the Indira Sagar dam and Omkareshwar dam projects subject to final orders to be passed by the Union Ministry of Environment and …
J. Venkatesan NEW DELHI: The Madhya Pradesh Government on Wednesday accused the Centre of filing a partisan affidavit to mislead the Supreme Court over the issue of canal work for the Indira Sagar and Omkareshwar dam projects. Senior counsel T. R. Andhyarujina, appearing for Madhya Pradesh, submitted before a three-judge …
J. Venkatesan New Delhi: Supporting social activist Medha Patkar, the Centre has filed an affidavit in the Supreme Court accusing the Madhya Pradesh government of not submitting the Command Area Development (CAD) plan before resorting to land acquisition and excavation for the Indira Sagar and Omkareshwar canals. A Bench of …
This is the second interim report of the committee constituted by the Ministry of Environment and Forests (vide O.M. No. 3-87/80-IA-I, dated 09.7.2008 superseded by O.M. of even number dated 02-09-2008 ) for assessing the status of compliance of environmental conditionalities and requirements to be fulfilled by project authorities of …
Mahim Pratap Singh BHOPAL: The Supreme Court has refused to vacate a Madhya Pradesh High Court stay on the Indira Sagar and Omkareshwar canals and directed the State Government to file by February 3 a detailed rejoinder to a counter-affidavit by Narmada Bachao Andolan. A Bench of Supreme Court Chief …
The Supreme Court on Tuesday asked the Madhya Pradesh government to file a list of persons facing displacement due to the multi-crore Indira Sagar and Onkareshwar canal projects, together with the rehabilitation package for them. A Special Bench led by CJI K G Balakrishnan was hearing a petition filed by …
Water governance in the Narmada river basin has been in the eye of a controversial storm from the time of independence. While initially the dispute had been between the riparian states over the apportionment of the use of the waters of the river for large dam centered canal irrigation and …
KHANDWA: Thousands of people displaced by the Indira Sagar and Omkareshwar dam projects in Madhya Pradesh took to the streets here on Wednesday protesting against
The Madhya Pradesh High Court on Friday directed the state Government to produce command area Plan for Omkareshwar dam and Indira Sagar dam projects constructed in Khandwa district. Hearing a petition of Narmada Bachao Andolan leader Medha Patkar and others, a division bench comprising Chief Justice A K Patnaik and …
Weir downstream of Srisailam dam among proposals. The Centre has been petitioned to allow diversion of 87.18 hectares of forestland for the Indira Sagar lift irrigation scheme. Our Bureau Hyderabad, June 7 The Andhra Pradesh Government has urged the Central Government to accord early clearance for several of its pending …
Keeping in view the ensuing monsoon a contingency plan would be implemented in the areas of various reservoirs of Narmada Valley. The plan would include safety masseurs and other basic requirement for the needy affected families, informed chairman of NVDA KL Agrawal here at Narmada Bhawan while reviewing the rehabilitation …
The officially appointed Environmental Expert Committee under the Chairmanship of Dr. Devendra Pandey, Director, Forest Survey of India to review the studies, planning and implementation of environmental safeguards for Sardar Sarovar and Indira Sagar Projects has submitted its Interim Report to the Ministry of Environment and Forests (MoEF). The Report …
The power generation capacity in the state has risen by 2937 megawatts during the last four years. With an extension unit of Amarkantak thermal power plant becoming critical soon, 210 MW more is going to be added to this capacity. Giving utmost importance to power, the state government has provided …