Lower Subansiri

Order of the National Green Tribunal regarding reconstitution of the Committee constituted by MoEF&CC for SLHEP, 31/07/2019

Order of the National Green Tribunal in the matter of Aabhijeet Sharma Vs Union of India & Others dated 31/07/2019. The applications seek reconstitution of the Committee constituted by the Ministry of Environment, Forest and Climate Change (MoEF&CC) in pursuance of order of the Tribunal dated 16.10.2017 for Subansiri Lower …

Order of the National Green Tribunal regarding reconstitution of the Committee constituted by MoEF&CC for SLHEP, 31/07/2019

Order of the National Green Tribunal in the matter of Aabhijeet Sharma Vs Union of India & Others dated 31/07/2019. The applications seek reconstitution of the Committee constituted by the Ministry of Environment, Forest and Climate Change (MoEF&CC) in pursuance of order of the Tribunal dated 16.10.2017 for Subansiri Lower …

NGT orders formation of expert panel to review Subansiri dam

The Eastern Zone bench of the National Green Tribunal (NGT) on Monday asked the Union ministry of environment and forests to constitute a threemember expert committee to review the Lower Subansiri Hydroelectric Project, work on which has been stalled since 2011over safety and environmental concerns. "The committee will consist of …

Judgement of the National Green Tribunal regarding the proposed Subansiri Lower Hydro Electric Project (SLHEP) threatening the ecology of lower Subansiri river, 16/10/2017

Judgement of the National Green Tribunal (Eastern Zone Bench, Kolkata) in the matter of Aabhijeet Sharma Vs Union of India & Others dated 16/10/2017 regarding the proposed Subansiri Lower Hydro Electric Project (SLHEP) located at the Assam Arunachal border with a 116 m high dam to generate 2000 mw of …

Opposition to hydel projects fuelled by narrow vested political interests: Pema Khandu

Arunachal Chief Minister Pema Khandu also said that people in his state often fall prey to misinformation and thus carry a lot of negative notions about large dams. Opposition to construction of hydro-electric projects with storage dams were fuelled by narrow vested political interests and hence required adequate awareness programmes …

Compensatory Afforestation

Compensatory afforestation is a dubious and controversial environmental “offset” that is adding to environmental damage instead of mitigating or compensating it. Compensatory afforestation may actually be accelerating the invasion of India’s forests by big corporations, in collusion with a permissive state, by legitimising the destruction of forests, greenwashing the land …

AJYCP stages protest against big dam construction

GOLAGHAT (Dhekial), Aug 3: The members of Assam Jatiyatabadi Yuba Chatra Parishad (AJYCP) Golaghat District Committee staged a protest near the Deputy Commissioner’s office in Golaghat on Thursday against the construction of the big dam of Lower Subansiri Hydro-electric Project. The AJYCP carried out a mass rally which was started …

Centre ignores State expert panel’s report

The Union Ministry of Forest, Environment and Climate Change (MoEFCC) has finally come up with the statement that it is not in favour of the report submitted by the Assam experts of the Project oversight Committee (PoC) on the Lower Subansiri Hydroelectric Power Project (LSHEP) and accepted the report of …

Order of the National Green Tribunal regarding Subansiri Lower Hydro-Electric Project in Assam, 31/05/2017

Order of the National Green Tribunal (Eastern Zone Bench, Kolkata) in the matter of Tularam Gogoi Vs Union of India & Others dated 31/05/2017 regarding Subansiri Lower Hydro-Electric Project in Assam. The Applicant (Tularam Gogoi) has questioned the Subansiri Lower Hydro-Electric Project in Assam on the ground that after the …

Assembly unanimous in expediting Subansiri project

NHPC has accepted recommendations of expert panels on downstream impact issue, Assam stands to get 533 MW power once project is completed: Pallab Lochon Das A consensus on early completion of the 2000 MW Lower Subansiri Hydel Project at Gerukamukh along Assam-Arunachal Pradesh border was struck among political parties in …

Centre seeks early start of hydro projects in State

The Centre is keen to start the hydro power projects in the state. Declaring that Arunachal is a priority state for development of hydro-power sector, Additional Secretary, Union Ministry of Power, B P Pandey in a meeting with state Chief Minister Pema Khandu recently said that the Centre has identified …

Plea to hold tripartite meet on Subansiri project

Opposition leader Debabrata Saikia has written a letter to Prime Minister Narendra Modi requesting to hold the much-delayed tripartite meeting for examining the expert committee report on the stalled 2,000MW NHPC Lower Subansiri hydroelectric project at Gerukamukh along Arunachal Pradesh border. Sakia in the letter to the PMO has stated …

Three hydro power projects at construction stage: NHPC

State-owned NHPC today said three hydro power projects, including Subansiri Lower, with an aggregate installed capacity of 3,130 mw are at the construction stage. Five future projects with a planned capacity of 4,995 MW are in process. A 50 mw wind power project in the Jaisalmer district of Rajasthan is …

Centre to take final call on Subansiri project

The Central Government will take the final call on the under-construction 2,000-MW Lower Subansiri Hydroelectric Power Project (LSHEP), even if a verdict to be passed by the National Green Tribunal (NGT) goes in favour of the project. Construction activities of the project have remained suspended since December 2011, following popular …

NHPC to raise Rs 4,500 cr after Subansiri project clearance

Following protests from pressure groups, project has been stalled since Dec 2011 on grounds that seismic activity could pose a risk to people in downstream areas As part of its Rs 3,000 crore diversification plan to venture into solar and wind power projects, NHPC Limited (previously known as National Hydroelectric …

Lower Subansiri hydroelectric power project completely safe, claims NHPC

National Hydro Power Corporation (NHPC) claims that the Lower Subansiri Hydro power project of 2000 Mega Watt is completely safe. The project has been designed to absorb floods to the tune of 500 cumecs over a 24-hour period. The current completion cost is Rs. 17,435 crore. The Executive Director of …

Upper Assam flood havoc due to constriction of Subansiri at dam site'

“The more NHPC and NEEPCO construct mega dams in Arunachal Pradesh, the more problems they create in Assam,” said the Siang Indigenous Farmers’ Forum (SIFF). Talking to newsmen today, SIFF general secretary Tasik Phangkam said: “The floods that have created a havoc in Upper Assam now are an enough an …

Agitators held for protests against hydroelectric project in Assam

Tezpur: Chatra Mukti Sangram Samitee (CMSS) members were on Thursday arrested at Gerukamukh while they were protesting against the ongoing construction of the 2000 mw Lower Subansiri Hydroelectric Power project (LSHEP) in Dhemaji district of Assam. The protesters were demonstrating against the NHPC starting reconstruction of the dam after it …

Dam experts' committee gives fractured opinion

The KMSS has said that the experts' committee on Lower Subansiri Hydroelectric Project along the Assam-Arunachal Pradesh border is divided in its opinion on the dam - while the local experts are against the dam with its present blueprint, the experts deputed by the Centre are in favour of going …

Efforts on to resume Subansiri dam construction: Tuki

More than three years since the construction of the 2,000 MW Subansiri Lower Hydroelectric Power Project (LSHEP) of NHPC came to a halt, Arunachal Chief Minister Nabam Tuki today told the State Assembly that all-out efforts were on for early resumption of construction works of the mega power project. Construction …

Green Tribunal seeks replies from parties

The National Green Tribunal (NGT) has directed the ministries of Environment and Forest, Power and the Brahmaputra Board to submit their replies within four weeks on the construction of big dams including the Subansiri (Lower) Hydropower Project. The NGT Kolkata Court of Justice Pratap Kumar Ray and Justice Dr PC …