Good Food is First Food. It is not junk food. It is the food that connects nature and nutrition with livelihoods. This food is good for our health; it comes from the rich biodiversity of our regions; it provides employment to people. Most importantly, cooking and eating give us pleasure. …
A report published by the Institute for Energy Economics and Financial Analysis (IEEFA) evaluating Tehri Hydro Development Corporation (THDC)’s proposed Khurja coal power plant in India finds the plant would push up the cost of electricity and increase air pollution at a time when the country’s renewable energy options are …
The capital saw the roll-out of the Graded Response Action Plan (GRAP) on Monday with a ban on use of diesel generator sets and the closure of the Badarpur thermal power plant, among others. The Supreme Court-mandated Environment Pollution Control) Authority said it would start receiving daily reports on enforcement …
NEW DELHI: After supplying power to the capital for over four decades, the Badarpur power station closed operations fully and permanently on Monday. The Supreme Court-appointed Environment Pollution (Prevention and Control) Authority (EPCA) had identified it as one of the biggest contributors to air pollution in Delhi and demanded its …
Two-fifths of China's coal power stations are loss-making and owners could save nearly $390 billion by closing plants in line with the Paris Climate Agreement, financial think-tank Carbon Tracker said on Thursday. The think tank undertook the first study to use satellite images to assess the everyday use and profitability …
The ambitious target of setting up 40 gw of rooftop solar power in the country by 2022 seems impossible with the government taking its 'eye' off this ambitious programme. "Rooftop solar has taken a back seat… The government has taken its eyes off rooftop solar," SunSource CEO, Adarsh Das told …
Coal-based power producers may find it difficult to meet the new emission standards target as banks are reluctant to give loans to buy equipment required to control emission. These power producers have to comply with new emission standards by 2022. However, bankers fear that if they lend more to the …
Power tariff touched a decade high of Rs 18 per unit in the spot market on Tuesday due to low hydro and wind energy production and coal shortage at thermal plants. "Spot power price for supply on Wednesday touched 10-year high of Rs 18 per unit in spot trading on …
Building work has restarted at hundreds of Chinese coal-fired power stations, according to an analysis of satellite imagery. The research, carried out by green campaigners CoalSwarm, suggests that 259 gigawatts of new capacity are under development in China. The authors say this is the same capacity to produce electricity as …
With Karnataka rejecting the draft notification, the Centre had asked the state to form a state-level committee to readdress the issue. BENGALURU: With the Karnataka government urging the Centre to constitute another committee on the declaration of Ecologically Sensitive Area (ESA) of Western Ghats, the Centre is likely to come …
State-run power producer NTPC has been given the green clearance for the Rs 7,732.35 crore expansion project of the Talcher Thermal Power Station in Odisha, a senior government official said Monday. The company's proposal is to add two additional units of 660 MW each in the existing premise of the …
MADURAI: Hundreds of fishermen and women on Monday staged a protest against the construction of a coal jetty in Kallamoli coastal village (between Manapad and Tiruchendur) for bringing coal to the upcoming 1,320 MW supercritical thermal power plant at Udangudi in Tuticorin district of Tamil Nadu. Hundreds of women from …
Nagpur: Fifty-seven units of the Centre-owned thermal power plants in the country have been given a deadline of 28 months to meet the emission norms for sulphur oxide and particulate matter. These plants are based in dense and ‘critically polluted areas’. During a recent hearing on a matter related to …
Order of the Supreme Court of India in the matter of M. C. Mehta Vs Union of India & Others dated 07/09/2018 regarding standards for thermal power plants which were to be implemented by December, 2017. Additional Solicitor General has stated before the Supreme Court that NTPC owns 48 units …
In 2015, under the United Nations Framework Convention on Climate Change’s Paris Agreement, governments committed to keeping global temperature increases to 2°C and to pursue efforts towards a more ambitious 1.5°C target. Global decarbonisation efforts may increase the risk of asset stranding – that is, loss of value, revenue or …
Patiala: With regulatory measures having failed to curtail instances of stubble burning, the Punjab government has put a ‘practical action plan’ to deal with the burning of crop residue. The state has drafted a two-year plan under which it would be spending Rs 665 crore on providing straw management machinery …
President of Mozambique Filipe Nyusi inaugurated on Wednesday in Maputo a new power plant that will generate 106 megawatts of electric power using gas to reinforce energy supply in the southern region of the country. Designed to meet 25 percent of the energy demand in the southern province of Maputo …
The Trump administration’s proposed replacement for the Obama-era’s central regulation on climate change, the Clean Power Plan, is expected to be released by the Environmental Protection Agency late next week, an agency source said on Thursday. The replacement for former President Barack Obama’s plan to slash carbon emissions from coal-fired …
China will work to improve the monitoring of emissions from heavy industries like steel, coal-fired power generation, coke and chemicals in key regions over the coming three years, stepping up an already-intensive campaign to tackle smog “There remain some outstanding problems in environmental monitoring, such as repeated data forgery and …
Most power plants are likely to miss the revised deadlines for complying with stricter air pollution emission norms, said Andrew DeLeone, Managing Director, GE Power India. “The biggest issue for India is that most of the power plants will miss the relaxed deadlines for compliance with stricter SOx, NOx emission …
Satellite imagery reveals that many coal-fired power projects that were halted by the Chinese government have quietly restarted. Analysis by CoalSwarm estimates that 46.7 gigawatts of new and restarted coal-fired power construction is visible based on satellite imagery supplied by Planet Labs. The coal-fired power plants are either generating power …